Live Practice Test

SSC CGL Pipes and Cisterns Practice Test 8

15 SSC CGL pipes and cisterns questions with chapter-wise explanations and exam-style options.

Timer-based practiceDetailed answer reviewMobile-friendly flow
SSC CGL Sponsor
High Intent Competitive Exam Traffic

Leaderboard slot above the practice session for revision tools, test series, books, and career products.

SSC CGL Practice Session

SSC CGL Pipes and Cisterns Practice Test 8

15 SSC CGL pipes and cisterns questions with chapter-wise explanations and exam-style options.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question ad-supported session
Preview all 15 questions in SSC CGL Pipes and Cisterns Practice Test 8 (no login required)
  1. Pipes and Cisterns

    1. A does a job in 8 days, B in 12 days. They work together and earn ₹750. B's share:

    • A. ₹250
    • B. ₹280
    • C. ₹300 (Correct)
    • D. ₹350

    Explanation: Ratio of work = 1/8:1/12=3:2. B's share=750×2/5=300.

  2. Pipes and Cisterns

    2. A alone can finish a work in 10 days. After A works for 4 days, B joins and they finish the remaining work in 2 more days. B alone can finish the work in:

    • A. 5 days (Correct)
    • B. 6 days
    • C. 8 days
    • D. 10 days

    Explanation: A completes 4/10 = 2/5 of the work. Remaining 3/5 is completed by A+B in 2 days, so their rate is 3/10. B's rate = 3/10 - 1/10 = 1/5.

  3. Pipes and Cisterns

    3. 24 men can complete a task in 16 days. 32 men will complete it in:

    • A. 10 days
    • B. 11 days
    • C. 12 days (Correct)
    • D. 14 days

    Explanation: 24×16=32×d → d=12 days.

  4. Pipes and Cisterns

    4. A is 3 times as fast as B. A takes 40 days less than B. Days to complete together:

    • A. 10 days
    • B. 12 days
    • C. 15 days (Correct)
    • D. 18 days

    Explanation: If B=x days, A=x/3. x−x/3=40 → 2x/3=40 → x=60. A=20 days. Together=1/20+1/60=4/60=1/15. 15 days.

  5. Pipes and Cisterns

    5. Two pipes A and B fill a tank in 15 and 20 minutes. When both are opened with a drain pipe C, the tank fills in 12 minutes. How long does C take to empty the full tank?

    • A. 24 min
    • B. 30 min (Correct)
    • C. 40 min
    • D. 60 min

    Explanation: A+B rate = 1/15 + 1/20 = 7/60. Net rate with drain = 1/12 = 5/60. Drain rate = 2/60 = 1/30, so C empties the tank in 30 minutes.

  6. Pipes and Cisterns

    6. A can do a piece of work in 12 days, working 8 hours a day. B can do same in 15 days working 6 hours a day. How many days for both working 9 hours a day?

    • A. 4 days
    • B. 5 days (Correct)
    • C. 6 days
    • D. 7 days

    Explanation: A: 96 man-hours. B: 90 man-hours. Total=186 man-hrs? No. Work by A=12×8=96 man-hrs per whole job. Work by B=15×6=90 man-hrs per whole job. So 1 man-hour=1/96 and 1/90 of job? No: same job in different man-hours doesn't work. A's work-rate=1/(12×8)=1/96 job/hour. B's=1/(15×6)=1/90. Together=1/96+1/90=(90+96)/(96×90)=186/8640=31/1440. Days at 9h/day=1/(31/1440×9)=1440/279≈5.16≈5 days.

  7. Pipes and Cisterns

    7. A works for 5 days, B for 8 days, and C for 10 days to complete a task. If A, B, C can individually do it in 20, 40, and 80 days respectively, how much work remains?

    • A. 0
    • B. 1/4
    • C. 1/8
    • D. None (Correct)

    Explanation: A:5/20=1/4, B:8/40=1/5, C:10/80=1/8. Total done=10/40+8/40+5/40=23/40. Remaining=17/40, which matches none of the listed options.

  8. Pipes and Cisterns

    8. If 10 men or 20 women can complete a job in 14 days, 5 men and 10 women will take:

    • A. 14 days (Correct)
    • B. 16 days
    • C. 18 days
    • D. 20 days

    Explanation: 1 man = 2 women. 5 men+10 women = 10+10=20 women. Same as 20 women → 14 days.

  9. Pipes and Cisterns

    9. Pipe A fills a tank in 20 hours. After 5 hours, pipe B also opens and the tank fills in 10 more hours. B alone fills the tank in:

    • A. 20 hours
    • B. 30 hours
    • C. 40 hours (Correct)
    • D. 50 hours

    Explanation: A fills 5/20 = 1/4 in 5 hours. Remaining 3/4 is filled by A+B in 10 hours, so A+B rate = 3/40. Since A rate is 1/20 = 2/40, B rate is 1/40.

  10. Pipes and Cisterns

    10. Three men A, B, C earn total ₹1080 in 9 days. A earns 3/4 of B, B earns 4/5 of C per day. C earns:

    • A. ₹40
    • B. ₹44
    • C. ₹48
    • D. ₹50 (Correct)

    Explanation: Let C=c per day. B=4c/5. A=3/4×4c/5=3c/5. Total per day=(3c/5+4c/5+c)=12c/5. 9×12c/5=1080 → c=1080×5/(9×12)=50. C per day=₹50.

  11. Pipes and Cisterns

    11. P alone can do a job in 12 days and Q alone in 16 days. They work alternately, starting with P. The job is completed in:

    • A. 13 days
    • B. 13 1/3 days (Correct)
    • C. 13 1/2 days
    • D. 14 days

    Explanation: In 12 days, six P-Q cycles complete 6 x (1/12 + 1/16) = 42/48 = 7/8 of the work. On day 13, P completes 1/12 more, leaving 1/24. Q takes (1/24)/(1/16) = 2/3 day, so total time is 13 1/3 days.

  12. Pipes and Cisterns

    12. Three pipes fill a tank in 6, 8, and 12 hours. All open together, tank fills in:

    • A. 2.18 hours
    • B. 2.67 hours (Correct)
    • C. 3 hours
    • D. 3.5 hours

    Explanation: 1/6+1/8+1/12=4/24+3/24+2/24=9/24=3/8. Time=8/3≈2.67 hours.

  13. Pipes and Cisterns

    13. A can do a work in 15 days and B in 20 days. They start together but A leaves 5 days before completion. Total days:

    • A. 10
    • B. 11 (Correct)
    • C. 12
    • D. 13

    Explanation: Let total days=d. Both work (d−5) days, then B alone 5 days. (d−5)/15+(d−5)/20+5/20=1. (d−5)(7/60)+1/4=1. (d−5)×7/60=3/4. d−5=45/7≈6.4. d≈11.4. Approx 11.

  14. Pipes and Cisterns

    14. 12 persons complete 60% of a work in 15 days. Extra persons needed to complete the rest in 8 days are:

    • A. 3 (Correct)
    • B. 4
    • C. 5
    • D. 6

    Explanation: 60% work needs 12 x 15 = 180 man-days, so full work needs 300 man-days. Remaining 40% needs 120 man-days. In 8 days, 15 persons are needed, so extra persons = 15 - 12 = 3.

  15. Pipes and Cisterns

    15. A and B together earn ₹560 in 7 days. A earns ₹40/day and B earns ₹x/day. Find x.

    • A. ₹30
    • B. ₹35
    • C. ₹40 (Correct)
    • D. ₹45

    Explanation: Total/day=560/7=80. B=80−40=₹40/day.