SSC CGL Time and Work Practice Test 27
15 original book-pattern SSC CGL questions on combined work, pipes, efficiency, wages, and alternate-day work.
Leaderboard slot above the practice session for revision tools, test series, books, and career products.
SSC CGL Time and Work Practice Test 27
15 original book-pattern SSC CGL questions on combined work, pipes, efficiency, wages, and alternate-day work.
Preview all 15 questions in SSC CGL Time and Work Practice Test 27 (no login required)
- Combined Work
1. A can complete a work in 18 days and B in 24 days. Working together, they finish the work in:
- A. 72/7 days (Correct)
- B. 80/7 days
- C. 84/7 days
- D. 90/7 days
Explanation: Combined rate = 1/18 + 1/24 = 7/72. Time = 72/7 days.
- One Leaves
2. A and B can finish a work in 20 days. They work together for 8 days, then A leaves. B completes the remaining work in 18 days. In how many days can B alone finish the work?
- A. 28 days
- B. 30 days (Correct)
- C. 32 days
- D. 36 days
Explanation: In 8 days, 8/20 = 2/5 work is done. Remaining 3/5 is done by B in 18 days, so B's full time = 18 x 5/3 = 30 days.
- Efficiency
3. A is 50% more efficient than B. If B completes a job in 30 days, A will complete it in:
- A. 18 days
- B. 20 days (Correct)
- C. 22 days
- D. 24 days
Explanation: A's efficiency is 1.5 times B's, so A's time = 30/1.5 = 20 days.
- Men and Days
4. 12 men can complete a work in 15 days. How many men are required to complete the same work in 9 days?
- A. 18
- B. 20 (Correct)
- C. 22
- D. 24
Explanation: Men x days is constant. Required men = 12 x 15 / 9 = 20.
- Pipes
5. A pipe fills a tank in 12 hours and another fills it in 18 hours. Together they fill the tank in:
- A. 36/5 hours (Correct)
- B. 40/5 hours
- C. 42/5 hours
- D. 45/5 hours
Explanation: Combined rate = 1/12 + 1/18 = 5/36. Time = 36/5 hours.
- Leakage
6. A pipe fills a tank in 10 hours, while a leak empties it in 15 hours. If both are open, the tank will fill in:
- A. 20 hours
- B. 25 hours
- C. 30 hours (Correct)
- D. 35 hours
Explanation: Net rate = 1/10 - 1/15 = 1/30, so time = 30 hours.
- Wages
7. A, B and C can complete a work in 12, 18 and 36 days respectively. If total wages are Rs. 3,300, B's share is:
- A. Rs. 800
- B. Rs. 900
- C. Rs. 1,000
- D. Rs. 1,100 (Correct)
Explanation: Efficiency ratio = 1/12:1/18:1/36 = 3:2:1. B gets 2/6 of 3300 = 1100.
- Alternate Days
8. A can do a work in 10 days and B in 15 days. They work on alternate days, starting with A. In how many days will the work be completed?
- A. 11 days
- B. 12 days (Correct)
- C. 13 days
- D. 14 days
Explanation: In 2 days they complete 1/10 + 1/15 = 1/6 work. In 10 days, 5/6 work is done. On day 11 A does 1/10, leaving 1/15, which B completes on day 12.
- Work Done
9. A can complete a job in 25 days. What fraction of work does A complete in 5 days?
- A. 1/6
- B. 1/5 (Correct)
- C. 1/4
- D. 1/3
Explanation: Work done in 5 days = 5/25 = 1/5.
- Capacity Change
10. 16 workers can finish a work in 24 days. After 6 days, 4 workers leave. How many more days are needed?
- A. 21
- B. 22
- C. 23
- D. 24 (Correct)
Explanation: Total work = 16 x 24 = 384 worker-days. Work done = 16 x 6 = 96. Remaining = 288. With 12 workers, time = 288/12 = 24 days.
- Work Ratio
11. A and B complete a work together in 16 days. If A alone takes 24 days, B alone will take:
- A. 36 days
- B. 40 days
- C. 44 days
- D. 48 days (Correct)
Explanation: B's rate = 1/16 - 1/24 = 1/48, so B takes 48 days.
- Pipes and Cisterns
12. Two pipes fill a tank in 8 hours and 12 hours. A third pipe empties it in 24 hours. If all are opened together, the tank fills in:
- A. 4 hours
- B. 5 hours
- C. 6 hours (Correct)
- D. 7 hours
Explanation: Net rate = 1/8 + 1/12 - 1/24 = 1/6, so time = 6 hours.
- Efficiency Ratio
13. The efficiencies of A and B are in the ratio 4:5. If A takes 25 days, B will take:
- A. 18 days
- B. 20 days (Correct)
- C. 22 days
- D. 24 days
Explanation: Time is inversely proportional to efficiency. B's time = 25 x 4/5 = 20 days.
- Partial Work
14. A can do 2/5 of a work in 8 days. How many days will A take to complete the whole work?
- A. 16 days
- B. 18 days
- C. 20 days (Correct)
- D. 22 days
Explanation: If 2/5 work takes 8 days, full work takes 8 x 5/2 = 20 days.
- Group Work
15. A, B and C can finish a work in 30, 40 and 60 days respectively. They work together for 5 days. What fraction of work remains?
- A. 1/2
- B. 7/12
- C. 5/8 (Correct)
- D. 2/3
Explanation: Combined rate = 1/30 + 1/40 + 1/60 = 3/40. In 5 days, work done = 15/40 = 3/8, so remaining work = 5/8.