SSC CGL Time and Work Practice Test 27

15 original book-pattern SSC CGL questions on combined work, pipes, efficiency, wages, and alternate-day work.

Timer-based practiceDetailed answer reviewMobile-friendly flow
SSC CGL Sponsor
High Intent Competitive Exam Traffic

Leaderboard slot above the practice session for revision tools, test series, books, and career products.

SSC CGL Practice Session

SSC CGL Time and Work Practice Test 27

15 original book-pattern SSC CGL questions on combined work, pipes, efficiency, wages, and alternate-day work.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question ad-supported session
Preview all 15 questions in SSC CGL Time and Work Practice Test 27 (no login required)
  1. Combined Work

    1. A can complete a work in 18 days and B in 24 days. Working together, they finish the work in:

    • A. 72/7 days (Correct)
    • B. 80/7 days
    • C. 84/7 days
    • D. 90/7 days

    Explanation: Combined rate = 1/18 + 1/24 = 7/72. Time = 72/7 days.

  2. One Leaves

    2. A and B can finish a work in 20 days. They work together for 8 days, then A leaves. B completes the remaining work in 18 days. In how many days can B alone finish the work?

    • A. 28 days
    • B. 30 days (Correct)
    • C. 32 days
    • D. 36 days

    Explanation: In 8 days, 8/20 = 2/5 work is done. Remaining 3/5 is done by B in 18 days, so B's full time = 18 x 5/3 = 30 days.

  3. Efficiency

    3. A is 50% more efficient than B. If B completes a job in 30 days, A will complete it in:

    • A. 18 days
    • B. 20 days (Correct)
    • C. 22 days
    • D. 24 days

    Explanation: A's efficiency is 1.5 times B's, so A's time = 30/1.5 = 20 days.

  4. Men and Days

    4. 12 men can complete a work in 15 days. How many men are required to complete the same work in 9 days?

    • A. 18
    • B. 20 (Correct)
    • C. 22
    • D. 24

    Explanation: Men x days is constant. Required men = 12 x 15 / 9 = 20.

  5. Pipes

    5. A pipe fills a tank in 12 hours and another fills it in 18 hours. Together they fill the tank in:

    • A. 36/5 hours (Correct)
    • B. 40/5 hours
    • C. 42/5 hours
    • D. 45/5 hours

    Explanation: Combined rate = 1/12 + 1/18 = 5/36. Time = 36/5 hours.

  6. Leakage

    6. A pipe fills a tank in 10 hours, while a leak empties it in 15 hours. If both are open, the tank will fill in:

    • A. 20 hours
    • B. 25 hours
    • C. 30 hours (Correct)
    • D. 35 hours

    Explanation: Net rate = 1/10 - 1/15 = 1/30, so time = 30 hours.

  7. Wages

    7. A, B and C can complete a work in 12, 18 and 36 days respectively. If total wages are Rs. 3,300, B's share is:

    • A. Rs. 800
    • B. Rs. 900
    • C. Rs. 1,000
    • D. Rs. 1,100 (Correct)

    Explanation: Efficiency ratio = 1/12:1/18:1/36 = 3:2:1. B gets 2/6 of 3300 = 1100.

  8. Alternate Days

    8. A can do a work in 10 days and B in 15 days. They work on alternate days, starting with A. In how many days will the work be completed?

    • A. 11 days
    • B. 12 days (Correct)
    • C. 13 days
    • D. 14 days

    Explanation: In 2 days they complete 1/10 + 1/15 = 1/6 work. In 10 days, 5/6 work is done. On day 11 A does 1/10, leaving 1/15, which B completes on day 12.

  9. Work Done

    9. A can complete a job in 25 days. What fraction of work does A complete in 5 days?

    • A. 1/6
    • B. 1/5 (Correct)
    • C. 1/4
    • D. 1/3

    Explanation: Work done in 5 days = 5/25 = 1/5.

  10. Capacity Change

    10. 16 workers can finish a work in 24 days. After 6 days, 4 workers leave. How many more days are needed?

    • A. 21
    • B. 22
    • C. 23
    • D. 24 (Correct)

    Explanation: Total work = 16 x 24 = 384 worker-days. Work done = 16 x 6 = 96. Remaining = 288. With 12 workers, time = 288/12 = 24 days.

  11. Work Ratio

    11. A and B complete a work together in 16 days. If A alone takes 24 days, B alone will take:

    • A. 36 days
    • B. 40 days
    • C. 44 days
    • D. 48 days (Correct)

    Explanation: B's rate = 1/16 - 1/24 = 1/48, so B takes 48 days.

  12. Pipes and Cisterns

    12. Two pipes fill a tank in 8 hours and 12 hours. A third pipe empties it in 24 hours. If all are opened together, the tank fills in:

    • A. 4 hours
    • B. 5 hours
    • C. 6 hours (Correct)
    • D. 7 hours

    Explanation: Net rate = 1/8 + 1/12 - 1/24 = 1/6, so time = 6 hours.

  13. Efficiency Ratio

    13. The efficiencies of A and B are in the ratio 4:5. If A takes 25 days, B will take:

    • A. 18 days
    • B. 20 days (Correct)
    • C. 22 days
    • D. 24 days

    Explanation: Time is inversely proportional to efficiency. B's time = 25 x 4/5 = 20 days.

  14. Partial Work

    14. A can do 2/5 of a work in 8 days. How many days will A take to complete the whole work?

    • A. 16 days
    • B. 18 days
    • C. 20 days (Correct)
    • D. 22 days

    Explanation: If 2/5 work takes 8 days, full work takes 8 x 5/2 = 20 days.

  15. Group Work

    15. A, B and C can finish a work in 30, 40 and 60 days respectively. They work together for 5 days. What fraction of work remains?

    • A. 1/2
    • B. 7/12
    • C. 5/8 (Correct)
    • D. 2/3

    Explanation: Combined rate = 1/30 + 1/40 + 1/60 = 3/40. In 5 days, work done = 15/40 = 3/8, so remaining work = 5/8.