SSC CGL Work and Efficiency Practice Test 1

15 SSC CGL work and efficiency questions with chapter-wise explanations and exam-style options.

Timer-based practiceDetailed answer reviewMobile-friendly flow
SSC CGL Sponsor
High Intent Competitive Exam Traffic

Leaderboard slot above the practice session for revision tools, test series, books, and career products.

SSC CGL Practice Session

SSC CGL Work and Efficiency Practice Test 1

15 SSC CGL work and efficiency questions with chapter-wise explanations and exam-style options.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question ad-supported session
Preview all 15 questions in SSC CGL Work and Efficiency Practice Test 1 (no login required)
  1. Work and Efficiency

    1. A can do a work in 12 days and B in 18 days. Together they can do it in:

    • A. 6.2 days
    • B. 7.2 days (Correct)
    • C. 8 days
    • D. 9 days

    Explanation: Combined rate = 1/12 + 1/18 = 5/36, so time = 36/5 = 7.2 days.

  2. Work and Efficiency

    2. If A does a work in 10 days, A's one-day work is:

    • A. 1/5
    • B. 1/10 (Correct)
    • C. 1/12
    • D. 1/15

    Explanation: One-day work is reciprocal of total days = 1/10.

  3. Work and Efficiency

    3. A pipe fills a tank in 6 hours and another empties it in 12 hours. If both are open, the tank fills in:

    • A. 6
    • B. 8
    • C. 10
    • D. 12 (Correct)

    Explanation: Net rate = 1/6 - 1/12 = 1/12, so time = 12 hours.

  4. Work and Efficiency

    4. If A is twice as efficient as B, then A:B working times are:

    • A. 1:2 (Correct)
    • B. 2:1
    • C. 1:4
    • D. 4:1

    Explanation: Time is inversely proportional to efficiency.

  5. Work and Efficiency

    5. If 5 men complete a work in 12 days, then 1 man will complete it in:

    • A. 50 days
    • B. 55 days
    • C. 60 days (Correct)
    • D. 65 days

    Explanation: Total man-days = 5 × 12 = 60.

  6. Work and Efficiency

    6. A completes a work in 10 days and B in 15 days. If they work on alternate days starting with A, the work finishes in:

    • A. 11 days
    • B. 12 days (Correct)
    • C. 13 days
    • D. 14 days

    Explanation: In 2 days they do 1/10 + 1/15 = 1/6. In 10 days they do 5/6. Remaining 1/6 is done in 2 more days with A then B pattern, so 12 days.

  7. Work and Efficiency

    7. Two pipes fill a tank in 20 and 30 minutes respectively. Together they fill it in:

    • A. 10 min
    • B. 12 min (Correct)
    • C. 15 min
    • D. 18 min

    Explanation: Combined rate = 1/20 + 1/30 = 1/12.

  8. Work and Efficiency

    8. A, B, and C can do a work in 12, 18, and 36 days respectively. Together they finish it in:

    • A. 4 days
    • B. 5 days
    • C. 6 days (Correct)
    • D. 7 days

    Explanation: 1/12 + 1/18 + 1/36 = 3/36 + 2/36 + 1/36 = 6/36 = 1/6, so the work finishes in 6 days.

  9. Work and Efficiency

    9. If A is thrice as efficient as B, then A can finish the work in 12 days and B in:

    • A. 24
    • B. 30
    • C. 36 (Correct)
    • D. 40

    Explanation: If A is 3 times efficient, B takes 3 times the time = 36 days.

  10. Work and Efficiency

    10. 15 workers can finish a work in 8 days. How many workers are needed to finish it in 6 days?

    • A. 18
    • B. 20 (Correct)
    • C. 22
    • D. 24

    Explanation: Workers × days = constant, so 15 × 8 / 6 = 20.

  11. Work and Efficiency

    11. A pipe fills a cistern in 4 hours and another in 6 hours. A waste pipe empties it in 12 hours. All three together fill it in:

    • A. 2 hours
    • B. 2.4 hours
    • C. 3 hours (Correct)
    • D. 3.5 hours

    Explanation: Net rate = 1/4 + 1/6 - 1/12 = 5/12 - 1/12 = 4/12 = 1/3, so time is 3 hours.

  12. Work and Efficiency

    12. If a man can do 1/20 of a work in a day, he will finish the whole work in:

    • A. 10
    • B. 15
    • C. 20 (Correct)
    • D. 25

    Explanation: Total time is reciprocal of one-day work = 20 days.

  13. Work and Efficiency

    13. A and B together do a work in 8 days. If A alone takes 24 days, B alone takes:

    • A. 10
    • B. 12 (Correct)
    • C. 16
    • D. 24

    Explanation: 1/B = 1/8 - 1/24 = 2/24 = 1/12, so B takes 12 days.

  14. Work and Efficiency

    14. A can do a work in 20 days. After working 5 days, B joins and they finish the remaining work in 5 days. B alone can do the work in:

    • A. 10 (Correct)
    • B. 15
    • C. 20
    • D. 25

    Explanation: A does 5/20 = 1/4 in 5 days, remaining = 3/4. A+B do 3/4 in 5 days, so rate = 3/20. B = 3/20 - 1/20 = 1/10, so B takes 10 days.

  15. Work and Efficiency

    15. 12 men or 18 women can complete a work in 10 days. Ratio of efficiency of a man to a woman is:

    • A. 2:3
    • B. 3:2 (Correct)
    • C. 3:5
    • D. 5:3

    Explanation: Since 12 men = 18 women, 1 man = 18/12 women = 3/2 women.