SSC CGL Work and Efficiency Practice Test 3

15 SSC CGL work and efficiency questions with chapter-wise explanations and exam-style options.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question ad-supported session
Preview all 15 questions in SSC CGL Work and Efficiency Practice Test 3 (no login required)
  1. Work and Efficiency

    1. A can do a work in 20 days and B in 30 days. Together they can do it in:

    • A. 10 days
    • B. 12 days (Correct)
    • C. 15 days
    • D. 18 days

    Explanation: Combined rate = 1/20 + 1/30 = 1/12.

  2. Work and Efficiency

    2. If A can do 1/16 of a work in a day, A alone can do the work in:

    • A. 12 days
    • B. 14 days
    • C. 16 days (Correct)
    • D. 18 days

    Explanation: Total days = reciprocal of one-day work.

  3. Work and Efficiency

    3. 12 men can complete a work in 18 days. 9 men will complete it in:

    • A. 20 days
    • B. 22 days
    • C. 24 days (Correct)
    • D. 26 days

    Explanation: Men x days = constant, so 12 x 18 / 9 = 24.

  4. Work and Efficiency

    4. Two pipes fill a tank in 10 hours and 15 hours. Together they fill it in:

    • A. 5 hours
    • B. 6 hours (Correct)
    • C. 7 hours
    • D. 8 hours

    Explanation: Combined rate = 1/10 + 1/15 = 1/6.

  5. Work and Efficiency

    5. If A is 50% more efficient than B, efficiency ratio A:B is:

    • A. 2:1
    • B. 3:2 (Correct)
    • C. 4:3
    • D. 5:4

    Explanation: 50% more means 150:100 = 3:2.

  6. Work and Efficiency

    6. A can do a work in 9 days and B in 18 days. Working on alternate days starting with A, the work finishes in:

    • A. 11 days
    • B. 12 days (Correct)
    • C. 13 days
    • D. 14 days

    Explanation: In 2 days they do 1/9 + 1/18 = 1/6. So in 12 days they finish the work.

  7. Work and Efficiency

    7. A, B, and C can complete a work in 10, 15, and 30 days respectively. Together they finish it in:

    • A. 5 days (Correct)
    • B. 6 days
    • C. 7 days
    • D. 8 days

    Explanation: 1/10 + 1/15 + 1/30 = 1/5.

  8. Work and Efficiency

    8. A pipe fills a tank in 5 hours and a waste pipe empties it in 20 hours. If both are open, tank fills in:

    • A. 5 hours
    • B. 6 2/3 hours (Correct)
    • C. 8 hours
    • D. 10 hours

    Explanation: Net rate = 1/5 - 1/20 = 3/20, so time = 20/3 hours.

  9. Work and Efficiency

    9. If A is 4 times as efficient as B and B takes 20 days, A takes:

    • A. 4 days
    • B. 5 days (Correct)
    • C. 6 days
    • D. 8 days

    Explanation: A takes one-fourth the time of B.

  10. Work and Efficiency

    10. A can do a work in 24 days. After 8 days, B joins and remaining work is finished in 8 days. B alone can do the work in:

    • A. 12 days
    • B. 16 days
    • C. 20 days
    • D. 24 days (Correct)

    Explanation: A does 1/3 in 8 days. Remaining 2/3 done in 8 days means A+B = 1/12. Since A = 1/24, B = 1/24.

  11. Work and Efficiency

    11. 15 workers can finish a work in 12 days. 20 workers can finish it in:

    • A. 8 days
    • B. 9 days (Correct)
    • C. 10 days
    • D. 11 days

    Explanation: 15 x 12 / 20 = 9.

  12. Work and Efficiency

    12. A tap fills a tank in 3 hours. In 1 hour it fills:

    • A. 1/2
    • B. 1/3 (Correct)
    • C. 1/4
    • D. 1/5

    Explanation: One-hour work = reciprocal of total time.

  13. Work and Efficiency

    13. If A does 25% more work than B in the same time, efficiency ratio A:B is:

    • A. 4:3
    • B. 5:4 (Correct)
    • C. 6:5
    • D. 7:6

    Explanation: 25% more means 125:100 = 5:4.

  14. Work and Efficiency

    14. A and B together can do a work in 6 days. If A alone takes 18 days, B alone takes:

    • A. 7 days
    • B. 8 days
    • C. 9 days (Correct)
    • D. 10 days

    Explanation: 1/B = 1/6 - 1/18 = 1/9.

  15. Work and Efficiency

    15. 8 men or 12 women can complete a work in the same time. Ratio of efficiency of a man to a woman is:

    • A. 2:3
    • B. 3:2 (Correct)
    • C. 4:3
    • D. 5:3

    Explanation: Since 8 men = 12 women, one man = 12/8 = 3/2 women.