Time & Work & Wages Test 15
Bilingual timed test for SSC, RRB and Banking quant with clean Hindi, preserved math symbols and detailed solutions.
Time & Work & Wages Test 15
25 bilingual MCQs from Time & Work & Wages, including 5 fresh LearnAtMyPlace original supplemental questions with detailed solutions. Designed for cross-exam quantitative aptitude practice with preserved ₹, ×, %, ratios and Hindi wording.
Question Palette Legend
Preview all 25 questions in Time & Work & Wages Test 15 (no login required)
- Time & Work & Wages — Three workers together
1. A, B and C can do a work in 17, 29 and 35 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 17, 29, 35 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 21461/2103 days
- B. 19358/2103 days
- C. 15152/2103 days
- D. 17255/2103 days (Correct)
Explanation: Combined rate = 1/17+1/29+1/35; time = 17255/2103 days. / संयुक्त दर = 1/17+1/29+1/35; समय = 17255/2103 days.
- Time & Work & Wages — Three workers together
2. A, B and C can do a work in 18, 30 and 36 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 18, 30, 36 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 67/7 days
- B. 53/7 days
- C. 74/7 days
- D. 60/7 days (Correct)
Explanation: Combined rate = 1/18+1/30+1/36; time = 60/7 days. / संयुक्त दर = 1/18+1/30+1/36; समय = 60/7 days.
- Time & Work & Wages — Work left after one worker
3. A can finish a work in 13 days and B in 28 days. A works for 7 days and leaves. How many more days will B take? / A काम को 13 दिनों में और B 28 दिनों में करता है। A 7 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 155/13 days
- B. 181/13 days
- C. 168/13 days (Correct)
- D. 194/13 days
Explanation: A completes 7/13. Remaining = 6/13. B takes 6/13×28 = 168/13 days. / A ने 7/13 काम किया। शेष = 6/13. B का समय = 6/13×28 = 168/13 days.
- Time & Work & Wages — Work left after one worker
4. A can finish a work in 14 days and B in 29 days. A works for 8 days and leaves. How many more days will B take? / A काम को 14 दिनों में और B 29 दिनों में करता है। A 8 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 101/7 days
- B. 87/7 days (Correct)
- C. 80/7 days
- D. 94/7 days
Explanation: A completes 8/14. Remaining = 3/7. B takes 3/7×29 = 87/7 days. / A ने 8/14 काम किया। शेष = 3/7. B का समय = 3/7×29 = 87/7 days.
- Time & Work & Wages — Alternate days work
5. A and B can finish a work in 22 and 28 days. They work on alternate days starting with A. Find total time. / A और B काम को 22 और 28 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 165/7 days
- B. 172/7 days (Correct)
- C. 186/7 days
- D. 179/7 days
Explanation: In two days work = 1/22+1/28. Counting cycles and the last partial day gives total time = 172/7 days. / दो दिनों का काम = 1/22+1/28. चक्रों और अंतिम आंशिक दिन से कुल समय = 172/7 days.
- Time & Work & Wages — Alternate days work
6. A and B can finish a work in 24 and 30 days. They work on alternate days starting with A. Find total time. / A और B काम को 24 और 30 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 128/5 days
- B. 133/5 days (Correct)
- C. 138/5 days
- D. 143/5 days
Explanation: In two days work = 1/24+1/30. Counting cycles and the last partial day gives total time = 133/5 days. / दो दिनों का काम = 1/24+1/30. चक्रों और अंतिम आंशिक दिन से कुल समय = 133/5 days.
- Time & Work & Wages — Efficiency change
7. A completes a work in 27 days. If efficiency increases by 25%, find new time. / A काम को 27 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 118/5 days
- B. 113/5 days
- C. 103/5 days
- D. 108/5 days (Correct)
Explanation: Time is inversely proportional to efficiency. New time = 27×100/125 = 108/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 27×100/125 = 108/5 days.
- Time & Work & Wages — Efficiency change
8. A completes a work in 28 days. If efficiency increases by 25%, find new time. / A काम को 28 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 117/5 days
- B. 112/5 days (Correct)
- C. 122/5 days
- D. 107/5 days
Explanation: Time is inversely proportional to efficiency. New time = 28×100/125 = 112/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 28×100/125 = 112/5 days.
- Time & Work & Wages — Partial wage sharing
9. A can complete work in 19 days, B in 16 days. A works 5 days and B works 7 days. Total wage is ₹5900. Find A's share. / A काम को 19 दिनों में और B 16 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹5900 है। A का हिस्सा ज्ञात करें।
- A. ₹2616
- B. ₹2016
- C. ₹2416
- D. ₹2216 (Correct)
Explanation: Wage ratio A:B = (5/19):(7/16) = 80:133. A's share = ₹2216. / वेतन अनुपात A:B = (5/19):(7/16) = 80:133. A का हिस्सा = ₹2216.
- Time & Work & Wages — Partial wage sharing
10. A can complete work in 10 days, B in 17 days. A works 5 days and B works 7 days. Total wage is ₹6000. Find A's share. / A काम को 10 दिनों में और B 17 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹6000 है। A का हिस्सा ज्ञात करें।
- A. ₹3690
- B. ₹3090
- C. ₹3290 (Correct)
- D. ₹3490
Explanation: Wage ratio A:B = (5/10):(7/17) = 17:14. A's share = ₹3290. / वेतन अनुपात A:B = (5/10):(7/17) = 17:14. A का हिस्सा = ₹3290.
- Time & Work & Wages — Three workers together
11. A, B and C can do a work in 15, 24 and 27 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 15, 24, 27 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 1080/157 days (Correct)
- B. 1237/157 days
- C. 923/157 days
- D. 1394/157 days
Explanation: Combined rate = 1/15+1/24+1/27; time = 1080/157 days. / संयुक्त दर = 1/15+1/24+1/27; समय = 1080/157 days.
- Time & Work & Wages — Three workers together
12. A, B and C can do a work in 16, 25 and 28 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 16, 25, 28 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 3574/387 days
- B. 2413/387 days
- C. 3187/387 days
- D. 2800/387 days (Correct)
Explanation: Combined rate = 1/16+1/25+1/28; time = 2800/387 days. / संयुक्त दर = 1/16+1/25+1/28; समय = 2800/387 days.
- Time & Work & Wages — Work left after one worker
13. A can finish a work in 13 days and B in 23 days. A works for 7 days and leaves. How many more days will B take? / A काम को 13 दिनों में और B 23 दिनों में करता है। A 7 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 138/13 days (Correct)
- B. 164/13 days
- C. 125/13 days
- D. 151/13 days
Explanation: A completes 7/13. Remaining = 6/13. B takes 6/13×23 = 138/13 days. / A ने 7/13 काम किया। शेष = 6/13. B का समय = 6/13×23 = 138/13 days.
- Time & Work & Wages — Work left after one worker
14. A can finish a work in 14 days and B in 24 days. A works for 8 days and leaves. How many more days will B take? / A काम को 14 दिनों में और B 24 दिनों में करता है। A 8 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 86/7 days
- B. 72/7 days (Correct)
- C. 79/7 days
- D. 65/7 days
Explanation: A completes 8/14. Remaining = 3/7. B takes 3/7×24 = 72/7 days. / A ने 8/14 काम किया। शेष = 3/7. B का समय = 3/7×24 = 72/7 days.
- Time & Work & Wages — Alternate days work
15. A and B can finish a work in 26 and 32 days. They work on alternate days starting with A. Find total time. / A और B काम को 26 और 32 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 229/8 days (Correct)
- B. 245/8 days
- C. 237/8 days
- D. 221/8 days
Explanation: In two days work = 1/26+1/32. Counting cycles and the last partial day gives total time = 229/8 days. / दो दिनों का काम = 1/26+1/32. चक्रों और अंतिम आंशिक दिन से कुल समय = 229/8 days.
- Time & Work & Wages — Alternate days work
16. A and B can finish a work in 12 and 18 days. They work on alternate days starting with A. Find total time. / A और B काम को 12 और 18 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 46/3 days
- B. 43/3 days (Correct)
- C. 40/3 days
- D. 49/3 days
Explanation: In two days work = 1/12+1/18. Counting cycles and the last partial day gives total time = 43/3 days. / दो दिनों का काम = 1/12+1/18. चक्रों और अंतिम आंशिक दिन से कुल समय = 43/3 days.
- Time & Work & Wages — Efficiency change
17. A completes a work in 27 days. If efficiency increases by 25%, find new time. / A काम को 27 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 103/5 days
- B. 118/5 days
- C. 113/5 days
- D. 108/5 days (Correct)
Explanation: Time is inversely proportional to efficiency. New time = 27×100/125 = 108/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 27×100/125 = 108/5 days.
- Time & Work & Wages — Efficiency change
18. A completes a work in 28 days. If efficiency increases by 25%, find new time. / A काम को 28 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 112/5 days (Correct)
- B. 122/5 days
- C. 117/5 days
- D. 107/5 days
Explanation: Time is inversely proportional to efficiency. New time = 28×100/125 = 112/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 28×100/125 = 112/5 days.
- Time & Work & Wages — Partial wage sharing
19. A can complete work in 19 days, B in 26 days. A works 5 days and B works 7 days. Total wage is ₹6900. Find A's share. / A काम को 19 दिनों में और B 26 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹6900 है। A का हिस्सा ज्ञात करें।
- A. ₹3211
- B. ₹3411 (Correct)
- C. ₹3611
- D. ₹3811
Explanation: Wage ratio A:B = (5/19):(7/26) = 130:133. A's share = ₹3411. / वेतन अनुपात A:B = (5/19):(7/26) = 130:133. A का हिस्सा = ₹3411.
- Time & Work & Wages — Partial wage sharing
20. A can complete work in 10 days, B in 15 days. A works 5 days and B works 7 days. Total wage is ₹5000. Find A's share. / A काम को 10 दिनों में और B 15 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹5000 है। A का हिस्सा ज्ञात करें।
- A. ₹2786
- B. ₹2386
- C. ₹2986
- D. ₹2586 (Correct)
Explanation: Wage ratio A:B = (5/10):(7/15) = 15:14. A's share = ₹2586. / वेतन अनुपात A:B = (5/10):(7/15) = 15:14. A का हिस्सा = ₹2586.
- Time & Work & Wages — Percentage / प्रतिशत
21. 12% of 650 is: / 650 का 12% कितना है?
- A. 68
- B. 78 (Correct)
- C. 88
- D. 98
Explanation: 12% = 12/100, so answer = 78. / प्रतिशत को 100 से भाग देकर मूल संख्या से गुणा करें।
- Time & Work & Wages — Profit-Loss / लाभ-हानि
22. An article bought for Rs 1150 is sold at 20% profit. Find SP. / Rs 1150 में खरीदी वस्तु 20% लाभ पर बेची गई। SP ज्ञात करें।
- A. Rs 1340
- B. Rs 1380 (Correct)
- C. Rs 1420
- D. Rs 1460
Explanation: SP = CP x (100 + profit%)/100 = 1150 x 120/100 = Rs 1380. / लाभ प्रतिशत जोड़कर विक्रय मूल्य निकालें।
- Time & Work & Wages — Time & Work / समय और कार्य
23. A finishes a work in 18 days and B in 24 days. Together they finish in: / A 18 दिन और B 24 दिन में काम पूरा करते हैं। साथ में समय?
- A. 9.3 days
- B. 10.3 days (Correct)
- C. 11.3 days
- D. 12.3 days
Explanation: Combined time = ab/(a+b) = 18 x 24 / 42 = 10.3 days. / संयुक्त कार्य में दरें जोड़ी जाती हैं।
- Time & Work & Wages — Speed Conversion / चाल परिवर्तन
24. 72 km/h equals: / 72 किमी/घंटा बराबर है:
- A. 17 m/s
- B. 20 m/s (Correct)
- C. 23 m/s
- D. 25 m/s
Explanation: km/h to m/s conversion uses x 5/18. 72 x 5/18 = 20. / किमी/घंटा को मी/से में बदलने के लिए 5/18 से गुणा करें।
- Time & Work & Wages — Simplification / सरलीकरण
25. Simplify: 18 x 12 + 18 - 12. / सरल करें: 18 x 12 + 18 - 12.
- A. 214
- B. 222 (Correct)
- C. 230
- D. 238
Explanation: Apply BODMAS: 216 + 18 - 12 = 222. / पहले गुणा, फिर जोड़-घटाव करें।