Time & Work & Wages Test 8
Bilingual timed test for SSC, RRB and Banking quant with clean Hindi, preserved math symbols and detailed solutions.
Time & Work & Wages Test 8
25 bilingual MCQs from Time & Work & Wages, including 5 fresh LearnAtMyPlace original supplemental questions with detailed solutions. Designed for cross-exam quantitative aptitude practice with preserved ₹, ×, %, ratios and Hindi wording.
Question Palette Legend
Preview all 25 questions in Time & Work & Wages Test 8 (no login required)
- Time & Work & Wages — Three workers together
1. A, B and C can do a work in 21, 24 and 39 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 21, 24, 39 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 1933/251 days
- B. 2686/251 days
- C. 2184/251 days (Correct)
- D. 2435/251 days
Explanation: Combined rate = 1/21+1/24+1/39; time = 2184/251 days. / संयुक्त दर = 1/21+1/24+1/39; समय = 2184/251 days.
- Time & Work & Wages — Three workers together
2. A, B and C can do a work in 22, 25 and 40 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 22, 25, 40 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 2686/243 days
- B. 1957/243 days
- C. 2443/243 days
- D. 2200/243 days (Correct)
Explanation: Combined rate = 1/22+1/25+1/40; time = 2200/243 days. / संयुक्त दर = 1/22+1/25+1/40; समय = 2200/243 days.
- Time & Work & Wages — Work left after one worker
3. A can finish a work in 13 days and B in 23 days. A works for 7 days and leaves. How many more days will B take? / A काम को 13 दिनों में और B 23 दिनों में करता है। A 7 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 138/13 days (Correct)
- B. 125/13 days
- C. 164/13 days
- D. 151/13 days
Explanation: A completes 7/13. Remaining = 6/13. B takes 6/13×23 = 138/13 days. / A ने 7/13 काम किया। शेष = 6/13. B का समय = 6/13×23 = 138/13 days.
- Time & Work & Wages — Work left after one worker
4. A can finish a work in 14 days and B in 24 days. A works for 8 days and leaves. How many more days will B take? / A काम को 14 दिनों में और B 24 दिनों में करता है। A 8 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 65/7 days
- B. 79/7 days
- C. 72/7 days (Correct)
- D. 86/7 days
Explanation: A completes 8/14. Remaining = 3/7. B takes 3/7×24 = 72/7 days. / A ने 8/14 काम किया। शेष = 3/7. B का समय = 3/7×24 = 72/7 days.
- Time & Work & Wages — Alternate days work
5. A and B can finish a work in 14 and 20 days. They work on alternate days starting with A. Find total time. / A और B काम को 14 और 20 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 82/5 days (Correct)
- B. 92/5 days
- C. 87/5 days
- D. 77/5 days
Explanation: In two days work = 1/14+1/20. Counting cycles and the last partial day gives total time = 82/5 days. / दो दिनों का काम = 1/14+1/20. चक्रों और अंतिम आंशिक दिन से कुल समय = 82/5 days.
- Time & Work & Wages — Alternate days work
6. A and B can finish a work in 16 and 22 days. They work on alternate days starting with A. Find total time. / A और B काम को 16 और 22 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 203/11 days (Correct)
- B. 192/11 days
- C. 214/11 days
- D. 225/11 days
Explanation: In two days work = 1/16+1/22. Counting cycles and the last partial day gives total time = 203/11 days. / दो दिनों का काम = 1/16+1/22. चक्रों और अंतिम आंशिक दिन से कुल समय = 203/11 days.
- Time & Work & Wages — Efficiency change
7. A completes a work in 27 days. If efficiency increases by 25%, find new time. / A काम को 27 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 103/5 days
- B. 113/5 days
- C. 118/5 days
- D. 108/5 days (Correct)
Explanation: Time is inversely proportional to efficiency. New time = 27×100/125 = 108/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 27×100/125 = 108/5 days.
- Time & Work & Wages — Efficiency change
8. A completes a work in 28 days. If efficiency increases by 25%, find new time. / A काम को 28 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 122/5 days
- B. 107/5 days
- C. 112/5 days (Correct)
- D. 117/5 days
Explanation: Time is inversely proportional to efficiency. New time = 28×100/125 = 112/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 28×100/125 = 112/5 days.
- Time & Work & Wages — Partial wage sharing
9. A can complete work in 19 days, B in 20 days. A works 5 days and B works 7 days. Total wage is ₹5900. Find A's share. / A काम को 19 दिनों में और B 20 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹5900 है। A का हिस्सा ज्ञात करें।
- A. ₹2332
- B. ₹2732
- C. ₹2932
- D. ₹2532 (Correct)
Explanation: Wage ratio A:B = (5/19):(7/20) = 100:133. A's share = ₹2532. / वेतन अनुपात A:B = (5/19):(7/20) = 100:133. A का हिस्सा = ₹2532.
- Time & Work & Wages — Partial wage sharing
10. A can complete work in 10 days, B in 21 days. A works 5 days and B works 7 days. Total wage is ₹6000. Find A's share. / A काम को 10 दिनों में और B 21 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹6000 है। A का हिस्सा ज्ञात करें।
- A. ₹3800
- B. ₹4000
- C. ₹3400
- D. ₹3600 (Correct)
Explanation: Wage ratio A:B = (5/10):(7/21) = 3:2. A's share = ₹3600. / वेतन अनुपात A:B = (5/10):(7/21) = 3:2. A का हिस्सा = ₹3600.
- Time & Work & Wages — Three workers together
11. A, B and C can do a work in 19, 19 and 31 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 19, 19, 31 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 589/81 days (Correct)
- B. 508/81 days
- C. 670/81 days
- D. 751/81 days
Explanation: Combined rate = 1/19+1/19+1/31; time = 589/81 days. / संयुक्त दर = 1/19+1/19+1/31; समय = 589/81 days.
- Time & Work & Wages — Three workers together
12. A, B and C can do a work in 20, 20 and 32 days respectively. Find the time taken together. / A, B और C काम को क्रमशः 20, 20, 32 दिनों में करते हैं। तीनों मिलकर समय ज्ञात करें।
- A. 181/21 days
- B. 160/21 days (Correct)
- C. 202/21 days
- D. 139/21 days
Explanation: Combined rate = 1/20+1/20+1/32; time = 160/21 days. / संयुक्त दर = 1/20+1/20+1/32; समय = 160/21 days.
- Time & Work & Wages — Work left after one worker
13. A can finish a work in 13 days and B in 18 days. A works for 7 days and leaves. How many more days will B take? / A काम को 13 दिनों में और B 18 दिनों में करता है। A 7 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 134/13 days
- B. 95/13 days
- C. 121/13 days
- D. 108/13 days (Correct)
Explanation: A completes 7/13. Remaining = 6/13. B takes 6/13×18 = 108/13 days. / A ने 7/13 काम किया। शेष = 6/13. B का समय = 6/13×18 = 108/13 days.
- Time & Work & Wages — Work left after one worker
14. A can finish a work in 14 days and B in 19 days. A works for 8 days and leaves. How many more days will B take? / A काम को 14 दिनों में और B 19 दिनों में करता है। A 8 दिन काम करके चला जाता है। शेष काम B कितने दिनों में करेगा?
- A. 64/7 days
- B. 57/7 days (Correct)
- C. 71/7 days
- D. 50/7 days
Explanation: A completes 8/14. Remaining = 3/7. B takes 3/7×19 = 57/7 days. / A ने 8/14 काम किया। शेष = 3/7. B का समय = 3/7×19 = 57/7 days.
- Time & Work & Wages — Alternate days work
15. A and B can finish a work in 18 and 24 days. They work on alternate days starting with A. Find total time. / A और B काम को 18 और 24 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 39/2 days
- B. 45/2 days
- C. 41/2 days (Correct)
- D. 43/2 days
Explanation: In two days work = 1/18+1/24. Counting cycles and the last partial day gives total time = 41/2 days. / दो दिनों का काम = 1/18+1/24. चक्रों और अंतिम आंशिक दिन से कुल समय = 41/2 days.
- Time & Work & Wages — Alternate days work
16. A and B can finish a work in 20 and 26 days. They work on alternate days starting with A. Find total time. / A और B काम को 20 और 26 दिनों में पूरा करते हैं। वे A से शुरू करके alternate days काम करते हैं। कुल समय ज्ञात करें।
- A. 319/13 days
- B. 293/13 days (Correct)
- C. 306/13 days
- D. 280/13 days
Explanation: In two days work = 1/20+1/26. Counting cycles and the last partial day gives total time = 293/13 days. / दो दिनों का काम = 1/20+1/26. चक्रों और अंतिम आंशिक दिन से कुल समय = 293/13 days.
- Time & Work & Wages — Efficiency change
17. A completes a work in 27 days. If efficiency increases by 25%, find new time. / A काम को 27 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 103/5 days
- B. 113/5 days
- C. 118/5 days
- D. 108/5 days (Correct)
Explanation: Time is inversely proportional to efficiency. New time = 27×100/125 = 108/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 27×100/125 = 108/5 days.
- Time & Work & Wages — Efficiency change
18. A completes a work in 28 days. If efficiency increases by 25%, find new time. / A काम को 28 दिनों में करता है। यदि दक्षता 25% बढ़े, तो नया समय ज्ञात करें।
- A. 112/5 days (Correct)
- B. 107/5 days
- C. 117/5 days
- D. 122/5 days
Explanation: Time is inversely proportional to efficiency. New time = 28×100/125 = 112/5 days. / समय दक्षता के व्युत्क्रमानुपाती है। नया समय = 28×100/125 = 112/5 days.
- Time & Work & Wages — Partial wage sharing
19. A can complete work in 19 days, B in 18 days. A works 5 days and B works 7 days. Total wage is ₹6900. Find A's share. / A काम को 19 दिनों में और B 18 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹6900 है। A का हिस्सा ज्ञात करें।
- A. ₹2985
- B. ₹3185
- C. ₹2585
- D. ₹2785 (Correct)
Explanation: Wage ratio A:B = (5/19):(7/18) = 90:133. A's share = ₹2785. / वेतन अनुपात A:B = (5/19):(7/18) = 90:133. A का हिस्सा = ₹2785.
- Time & Work & Wages — Partial wage sharing
20. A can complete work in 10 days, B in 19 days. A works 5 days and B works 7 days. Total wage is ₹5000. Find A's share. / A काम को 10 दिनों में और B 19 दिनों में करता है। A 5 दिन और B 7 दिन काम करते हैं। कुल मजदूरी ₹5000 है। A का हिस्सा ज्ञात करें।
- A. ₹2679
- B. ₹3279
- C. ₹2879 (Correct)
- D. ₹3079
Explanation: Wage ratio A:B = (5/10):(7/19) = 19:14. A's share = ₹2879. / वेतन अनुपात A:B = (5/10):(7/19) = 19:14. A का हिस्सा = ₹2879.
- Time & Work & Wages — Percentage / प्रतिशत
21. 15% of 825 is: / 825 का 15% कितना है?
- A. 113.75
- B. 123.75 (Correct)
- C. 133.75
- D. 143.75
Explanation: 15% = 15/100, so answer = 123.75. / प्रतिशत को 100 से भाग देकर मूल संख्या से गुणा करें।
- Time & Work & Wages — Profit-Loss / लाभ-हानि
22. An article bought for Rs 800 is sold at 10% profit. Find SP. / Rs 800 में खरीदी वस्तु 10% लाभ पर बेची गई। SP ज्ञात करें।
- A. Rs 840
- B. Rs 880 (Correct)
- C. Rs 920
- D. Rs 960
Explanation: SP = CP x (100 + profit%)/100 = 800 x 110/100 = Rs 880. / लाभ प्रतिशत जोड़कर विक्रय मूल्य निकालें।
- Time & Work & Wages — Time & Work / समय और कार्य
23. A finishes a work in 21 days and B in 27 days. Together they finish in: / A 21 दिन और B 27 दिन में काम पूरा करते हैं। साथ में समय?
- A. 10.8 days
- B. 11.8 days (Correct)
- C. 12.8 days
- D. 13.8 days
Explanation: Combined time = ab/(a+b) = 21 x 27 / 48 = 11.8 days. / संयुक्त कार्य में दरें जोड़ी जाती हैं।
- Time & Work & Wages — Speed Conversion / चाल परिवर्तन
24. 90 km/h equals: / 90 किमी/घंटा बराबर है:
- A. 22 m/s
- B. 25 m/s (Correct)
- C. 28 m/s
- D. 30 m/s
Explanation: km/h to m/s conversion uses x 5/18. 90 x 5/18 = 25. / किमी/घंटा को मी/से में बदलने के लिए 5/18 से गुणा करें।
- Time & Work & Wages — Simplification / सरलीकरण
25. Simplify: 25 x 12 + 25 - 12. / सरल करें: 25 x 12 + 25 - 12.
- A. 305
- B. 313 (Correct)
- C. 321
- D. 329
Explanation: Apply BODMAS: 300 + 25 - 12 = 313. / पहले गुणा, फिर जोड़-घटाव करें।