RRB NTPC Time-Work Bilingual Test 16
Time & Work / समय और कार्य practice in Hindi-English with original RRB NTPC style questions, timer, negative marking and explanation review.
RRB NTPC Time-Work Bilingual Test 16
Efficiency, combined work, pipes and man-days. Test 16 contains original bilingual RRB NTPC style questions with explanations. Use it as a short railway CBT drill: solve, submit, review every explanation, then move to the next set.
Question Palette Legend
Preview all 18 questions in RRB NTPC Time-Work Bilingual Test 16 (no login required)
- Mathematics / गणित — Combined Work
1. A in 15 days, B in 30 days. Together? / A 15 दिन, B 30 दिन। साथ में?
- A. 8
- B. 10 (Correct)
- C. 12
- D. 15
Explanation: Rate = 1/15 + 1/30 = 1/10. / संयुक्त दर।
- Mathematics / गणित — Efficiency
2. Efficiency A:B = 4:3, together 14 days. A alone? / दक्षता 4:3, साथ में 14 दिन। A अकेला?
- A. 20.5
- B. 22.5
- C. 24.5 (Correct)
- D. 26.5
Explanation: Work = 7 x 14 = 98; A time = 98/4 = 24.5. / दक्षता विधि।
- Mathematics / गणित — Pipes
3. Two pipes fill in 12h and 24h. Together? / पाइप 12h और 24h में भरते हैं। साथ में?
- A. 6h
- B. 8h (Correct)
- C. 9h
- D. 10h
Explanation: Rate = 1/12 + 1/24 = 1/8. / संयुक्त दर।
- Mathematics / गणित — Work Left
4. A finishes in 18 days. Work left after 6 days? / 18 दिन में कार्य, 6 दिन बाद शेष?
- A. 1/3
- B. 1/2
- C. 2/3 (Correct)
- D. 3/4
Explanation: Done 6/18 = 1/3, left 2/3. / शेष।
- Mathematics / गणित — Man-days
5. 15 workers finish in 12 days. 20 workers finish in? / 15 मजदूर 12 दिन, 20 मजदूर?
- A. 8
- B. 9 (Correct)
- C. 10
- D. 11
Explanation: Worker-days = 180, days = 180/20 = 9. / मानव-दिन।
- Quantitative Aptitude / मात्रात्मक योग्यता — Combined Work / संयुक्त कार्य
6. A completes a work in 12 days and B in 18 days. Find time together. / A कार्य 12 दिन में और B 18 दिन में करता है। साथ में समय?
- A. 6.8 days
- B. 7.2 days (Correct)
- C. 8 days
- D. 9 days
Explanation: Rate = 1/12 + 1/18 = 5/36, so time = 36/5 = 7.2 days. / कार्य-दर जोड़ें।
- Quantitative Aptitude / मात्रात्मक योग्यता — Efficiency / दक्षता
7. A:B efficiency = 3:2. Together finish in 10 days. A alone takes: / A:B दक्षता 3:2 है। साथ में 10 दिन लगते हैं। A अकेला?
- A. 15 days
- B. 16.67 days (Correct)
- C. 20 days
- D. 25 days
Explanation: Total work = 5 x 10 = 50 units; A time = 50/3 = 16.67. / दक्षता विधि लगाएँ।
- Quantitative Aptitude / मात्रात्मक योग्यता — Pipes / पाइप
8. A fills a tank in 10 h and B empties it in 20 h. Net filling time? / A टंकी 10 h में भरता है और B 20 h में खाली करता है। कुल समय?
- A. 10 h
- B. 15 h
- C. 20 h (Correct)
- D. 25 h
Explanation: Net rate = 1/10 - 1/20 = 1/20. / भरने और खाली करने की दर घटाएँ।
- Quantitative Aptitude / मात्रात्मक योग्यता — Man-days / मानव-दिन
9. 8 workers finish work in 15 days. 12 workers finish it in: / 8 मजदूर 15 दिन में कार्य करते हैं। 12 मजदूर कितने दिन लेंगे?
- A. 8
- B. 10 (Correct)
- C. 12
- D. 14
Explanation: Worker-days = 8 x 15 = 120; days = 120/12 = 10. / मानव-दिन समान रहते हैं।
- Quantitative Aptitude / मात्रात्मक योग्यता — Work Left / शेष कार्य
10. A can finish work in 18 days. Work left after 6 days is: / A कार्य 18 दिन में करता है। 6 दिन बाद शेष कार्य?
- A. 1/3
- B. 1/2
- C. 2/3 (Correct)
- D. 3/4
Explanation: Done = 6/18 = 1/3, so left = 2/3. / किया गया भाग घटाएँ।
- Quantitative Aptitude / मात्रात्मक योग्यता — Wages / मजदूरी
11. A and B earn Rs 900 in work ratio 4:5. Find B's share. / A और B Rs 900 को कार्य अनुपात 4:5 में बाँटते हैं। B का हिस्सा?
- A. Rs 400
- B. Rs 450
- C. Rs 500 (Correct)
- D. Rs 550
Explanation: B share = 5/9 x 900 = 500. / मजदूरी कार्य अनुपात में बँटती है।
- Quantitative Aptitude / मात्रात्मक योग्यता — Alternate Days / वैकल्पिक दिन
12. A can do a work in 10 days and B in 15 days. Working on alternate days starting with A, work finishes in: / A 10 दिन और B 15 दिन में कार्य करता है। A से शुरू कर बारी-बारी काम करने पर समय?
- A. 11 days
- B. 12 days (Correct)
- C. 13 days
- D. 14 days
Explanation: In 2 days work done = 1/10 + 1/15 = 1/6; total time = 12 days. / 2-दिन का चक्र 1/6 कार्य करता है।
- Quantitative Aptitude / मात्रात्मक योग्यता — Pipe Filling / पाइप भरना
13. Two pipes fill a tank in 12 h and 24 h. Together they fill it in: / दो पाइप 12 h और 24 h में टंकी भरते हैं। साथ में समय?
- A. 6 h
- B. 8 h (Correct)
- C. 9 h
- D. 10 h
Explanation: Rate = 1/12 + 1/24 = 1/8. / संयुक्त दर 1/8 है।
- Quantitative Aptitude / मात्रात्मक योग्यता — Efficiency Ratio / दक्षता अनुपात
14. A is twice as efficient as B. Together they finish in 12 days. B alone takes: / A, B से दोगुना दक्ष है। दोनों 12 दिन में कार्य करते हैं। B अकेला?
- A. 24 days
- B. 30 days
- C. 36 days (Correct)
- D. 40 days
Explanation: Efficiencies 2:1; total work = 3 x 12 = 36 units, B time = 36. / B की दक्षता 1 इकाई है।
- Quantitative Aptitude / मात्रात्मक योग्यता — Work Fraction / कार्य भिन्न
15. If A completes 1/5 of work in one day, he completes whole work in: / A एक दिन में 1/5 कार्य करता है। पूरा कार्य कितने दिन में?
- A. 3
- B. 4
- C. 5 (Correct)
- D. 6
Explanation: Time is reciprocal of one-day work = 5 days. / दर का व्युत्क्रम लें।
- Quantitative Aptitude / मात्रात्मक योग्यता — Leakage / रिसाव
16. A pipe fills a tank in 8 h. A leak empties it in 24 h. Net filling time is: / पाइप 8 h में भरता है और रिसाव 24 h में खाली करता है। कुल समय?
- A. 10 h
- B. 12 h (Correct)
- C. 14 h
- D. 16 h
Explanation: Net rate = 1/8 - 1/24 = 1/12. / दर घटाएँ।
- Quantitative Aptitude / मात्रात्मक योग्यता — Team Work / दल कार्य
17. A, B and C can do work in 12, 15 and 20 days. Together they take: / A, B, C कार्य 12, 15, 20 दिन में करते हैं। साथ में समय?
- A. 4 days
- B. 5 days (Correct)
- C. 6 days
- D. 7 days
Explanation: Rate = 1/12 + 1/15 + 1/20 = 1/5. / संयुक्त दर 1/5 है।
- Quantitative Aptitude / मात्रात्मक योग्यता — Work Rate / कार्य दर
18. If 6 men do a work in 8 days, how many man-days are needed? / 6 व्यक्ति 8 दिन में कार्य करते हैं। कितने मानव-दिन लगेंगे?
- A. 36
- B. 42
- C. 48 (Correct)
- D. 56
Explanation: Man-days = 6 x 8 = 48. / व्यक्ति x दिन करें।