Live Practice Test

SSC CGL Time and Work Verified Practice Test 1

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Practice and revisionDetailed answer reviewMobile-friendly flow
SSC CGL Practice Session

SSC CGL Time and Work Verified Practice Test 1

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question practice session
Preview all 15 questions in SSC CGL Time and Work Verified Practice Test 1 (no login required)
  1. Combined Work

    1. A can complete a work in 18 days and B in 24 days. Working together, they finish the work in:

    • A. 72/7 days (Correct)
    • B. 80/7 days
    • C. 84/7 days
    • D. 90/7 days

    Explanation: Combined rate = 1/18 + 1/24 = 7/72. Time = 72/7 days.

  2. One Leaves

    2. A and B can finish a work in 20 days. They work together for 8 days, then A leaves. B completes the remaining work in 18 days. In how many days can B alone finish the work?

    • A. 28 days
    • B. 30 days (Correct)
    • C. 32 days
    • D. 36 days

    Explanation: In 8 days, 8/20 = 2/5 work is done. Remaining 3/5 is done by B in 18 days, so B's full time = 18 x 5/3 = 30 days.

  3. Efficiency

    3. A is 50% more efficient than B. If B completes a job in 30 days, A will complete it in:

    • A. 18 days
    • B. 20 days (Correct)
    • C. 22 days
    • D. 24 days

    Explanation: A's efficiency is 1.5 times B's, so A's time = 30/1.5 = 20 days.

  4. Men and Days

    4. 12 men can complete a work in 15 days. How many men are required to complete the same work in 9 days?

    • A. 18
    • B. 20 (Correct)
    • C. 22
    • D. 24

    Explanation: Men x days is constant. Required men = 12 x 15 / 9 = 20.

  5. Pipes

    5. A pipe fills a tank in 12 hours and another fills it in 18 hours. Together they fill the tank in:

    • A. 36/5 hours (Correct)
    • B. 40/5 hours
    • C. 42/5 hours
    • D. 45/5 hours

    Explanation: Combined rate = 1/12 + 1/18 = 5/36. Time = 36/5 hours.

  6. Leakage

    6. A pipe fills a tank in 10 hours, while a leak empties it in 15 hours. If both are open, the tank will fill in:

    • A. 20 hours
    • B. 25 hours
    • C. 30 hours (Correct)
    • D. 35 hours

    Explanation: Net rate = 1/10 - 1/15 = 1/30, so time = 30 hours.

  7. Wages

    7. A, B and C can complete a work in 12, 18 and 36 days respectively. If total wages are Rs. 3,300, B's share is:

    • A. Rs. 800
    • B. Rs. 900
    • C. Rs. 1,000
    • D. Rs. 1,100 (Correct)

    Explanation: Efficiency ratio = 1/12:1/18:1/36 = 3:2:1. B gets 2/6 of 3300 = 1100.

  8. Alternate Days

    8. A can do a work in 10 days and B in 15 days. They work on alternate days, starting with A. In how many days will the work be completed?

    • A. 11 days
    • B. 12 days (Correct)
    • C. 13 days
    • D. 14 days

    Explanation: In 2 days they complete 1/10 + 1/15 = 1/6 work. In 10 days, 5/6 work is done. On day 11 A does 1/10, leaving 1/15, which B completes on day 12.

  9. Work Done

    9. A can complete a job in 25 days. What fraction of work does A complete in 5 days?

    • A. 1/6
    • B. 1/5 (Correct)
    • C. 1/4
    • D. 1/3

    Explanation: Work done in 5 days = 5/25 = 1/5.

  10. Capacity Change

    10. 16 workers can finish a work in 24 days. After 6 days, 4 workers leave. How many more days are needed?

    • A. 21
    • B. 22
    • C. 23
    • D. 24 (Correct)

    Explanation: Total work = 16 x 24 = 384 worker-days. Work done = 16 x 6 = 96. Remaining = 288. With 12 workers, time = 288/12 = 24 days.

  11. Work Ratio

    11. A and B complete a work together in 16 days. If A alone takes 24 days, B alone will take:

    • A. 36 days
    • B. 40 days
    • C. 44 days
    • D. 48 days (Correct)

    Explanation: B's rate = 1/16 - 1/24 = 1/48, so B takes 48 days.

  12. Pipes and Cisterns

    12. Two pipes fill a tank in 8 hours and 12 hours. A third pipe empties it in 24 hours. If all are opened together, the tank fills in:

    • A. 4 hours
    • B. 5 hours
    • C. 6 hours (Correct)
    • D. 7 hours

    Explanation: Net rate = 1/8 + 1/12 - 1/24 = 1/6, so time = 6 hours.

  13. Efficiency Ratio

    13. The efficiencies of A and B are in the ratio 4:5. If A takes 25 days, B will take:

    • A. 18 days
    • B. 20 days (Correct)
    • C. 22 days
    • D. 24 days

    Explanation: Time is inversely proportional to efficiency. B's time = 25 x 4/5 = 20 days.

  14. Partial Work

    14. A can do 2/5 of a work in 8 days. How many days will A take to complete the whole work?

    • A. 16 days
    • B. 18 days
    • C. 20 days (Correct)
    • D. 22 days

    Explanation: If 2/5 work takes 8 days, full work takes 8 x 5/2 = 20 days.

  15. Group Work

    15. A, B and C can finish a work in 30, 40 and 60 days respectively. They work together for 5 days. What fraction of work remains?

    • A. 1/2
    • B. 7/12
    • C. 5/8 (Correct)
    • D. 2/3

    Explanation: Combined rate = 1/30 + 1/40 + 1/60 = 3/40. In 5 days, work done = 15/40 = 3/8, so remaining work = 5/8.