SSC CGL Practice Session

SSC CGL Time and Work Practice Test 2

15 additional SSC CGL questions on work rates, pipes, efficiency, and combined work patterns.

Questions
14
Marking
+2 correct, -0.5 wrong
Format
15-question ad-supported session
Preview all 14 questions in SSC CGL Time and Work Practice Test 2 (no login required)
  1. Combined Work

    1. A can do a work in 15 days and B in 10 days. Together they can do it in:

    • A. 5 days
    • B. 6 days (Correct)
    • C. 7 days
    • D. 8 days

    Explanation: Combined rate = 1/15 + 1/10 = 1/6.

  2. Efficiency

    2. If A completes 1/8 of a work in a day, A can finish it in:

    • A. 6 days
    • B. 7 days
    • C. 8 days (Correct)
    • D. 9 days

    Explanation: Total time is reciprocal of one-day work.

  3. Man-days

    3. 8 men can complete a work in 15 days. 12 men will complete it in:

    • A. 8 days
    • B. 9 days
    • C. 10 days (Correct)
    • D. 12 days

    Explanation: Men x days = constant, so 8 x 15 / 12 = 10.

  4. Pipes

    4. A pipe fills a tank in 8 hours and another in 12 hours. Together they fill it in:

    • A. 4.8 hours (Correct)
    • B. 5 hours
    • C. 6 hours
    • D. 7 hours

    Explanation: Combined rate = 1/8 + 1/12 = 5/24, so time = 24/5 hours.

  5. Efficiency Ratio

    5. If A is twice as efficient as B, the ratio of time taken by A and B is:

    • A. 1:2 (Correct)
    • B. 2:1
    • C. 1:4
    • D. 4:1

    Explanation: Time is inversely proportional to efficiency.

  6. Alternate Days

    6. A can do a work in 12 days and B in 18 days. Working on alternate days starting with A, the work completes in:

    • A. 13 days
    • B. 14 days
    • C. 15 days (Correct)
    • D. 16 days

    Explanation: In 2 days they do 3/36 + 2/36 = 5/36. In 12 days (6 cycles) 30/36 is done. Day 13 (A): 3/36 more, total 33/36. Day 14 (B): 2/36 more, total 35/36. Day 15 (A): finishes remaining 1/36. Work is done in 15 days.

  7. Work Sharing

    7. A, B, and C can complete a work in 12, 15, and 20 days respectively. Together they finish it in:

    • A. 4 days
    • B. 5 days (Correct)
    • C. 6 days
    • D. 7 days

    Explanation: 1/12 + 1/15 + 1/20 = 1/5.

  8. Pipes and Waste

    8. A pipe fills a tank in 6 hours and a waste pipe empties it in 9 hours. If both are open, the tank fills in:

    • A. 12 hours
    • B. 15 hours
    • C. 18 hours (Correct)
    • D. 20 hours

    Explanation: Net rate = 1/6 - 1/9 = 1/18.

  9. Wages

    9. If A is thrice as efficient as B, and B takes 24 days, A takes:

    • A. 6 days
    • B. 8 days (Correct)
    • C. 10 days
    • D. 12 days

    Explanation: A takes one-third the time of B.

  10. Part Work

    10. A can do a work in 20 days. After 5 days, B joins and the work finishes in 5 more days. B alone can do the work in:

    • A. 10 days (Correct)
    • B. 12 days
    • C. 15 days
    • D. 20 days

    Explanation: A does 1/4 in 5 days. Remaining 3/4 is done in 5 days, so A+B = 3/20. Therefore B = 1/10.

  11. Group Work

    11. 10 men can complete a work in 18 days. 15 men can complete it in:

    • A. 10 days
    • B. 12 days (Correct)
    • C. 14 days
    • D. 16 days

    Explanation: 10 x 18 / 15 = 12.

  12. Pipes

    12. A tap fills a bucket in 4 minutes. In 1 minute it fills:

    • A. 1/2
    • B. 1/3
    • C. 1/4 (Correct)
    • D. 1/5

    Explanation: One-minute work is reciprocal of total time.

  13. Efficiency

    13. If A does 60% more work than B in the same time, efficiency ratio A:B is:

    • A. 3:2
    • B. 4:3
    • C. 5:4
    • D. 8:5 (Correct)

    Explanation: 60% more means 160:100 = 8:5.

  14. Combined Work

    14. A and B together can do a work in 8 days. If A alone takes 24 days, B alone takes:

    • A. 10 days
    • B. 12 days (Correct)
    • C. 16 days
    • D. 20 days

    Explanation: 1/B = 1/8 - 1/24 = 1/12.