Live Practice Test

SSC CGL Time and Work Verified Practice Test 2

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Practice and revisionDetailed answer reviewMobile-friendly flow
SSC CGL Practice Session

SSC CGL Time and Work Verified Practice Test 2

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question practice session
Preview all 15 questions in SSC CGL Time and Work Verified Practice Test 2 (no login required)
  1. Combined Work

    1. A can do a work in 12 days and B in 18 days. Together they can do it in:

    • A. 6.2 days
    • B. 7.2 days (Correct)
    • C. 8 days
    • D. 9 days

    Explanation: Combined rate = 1/12 + 1/18 = 5/36, so time = 36/5 = 7.2 days.

  2. Efficiency

    2. If A does a work in 10 days, A's one-day work is:

    • A. 1/5
    • B. 1/10 (Correct)
    • C. 1/12
    • D. 1/15

    Explanation: One-day work is reciprocal of total days = 1/10.

  3. Pipes and Cisterns

    3. A pipe fills a tank in 6 hours and another empties it in 12 hours. If both are open, the tank fills in:

    • A. 6
    • B. 8
    • C. 10
    • D. 12 (Correct)

    Explanation: Net rate = 1/6 - 1/12 = 1/12, so time = 12 hours.

  4. Wages

    4. If A is twice as efficient as B, then A:B working times are:

    • A. 1:2 (Correct)
    • B. 2:1
    • C. 1:4
    • D. 4:1

    Explanation: Time is inversely proportional to efficiency.

  5. Combined Work

    5. If 5 men complete a work in 12 days, then 1 man will complete it in:

    • A. 50 days
    • B. 55 days
    • C. 60 days (Correct)
    • D. 65 days

    Explanation: Total man-days = 5 × 12 = 60.

  6. Alternate Days

    6. A completes a work in 10 days and B in 15 days. If they work on alternate days starting with A, the work finishes in:

    • A. 11 days
    • B. 12 days (Correct)
    • C. 13 days
    • D. 14 days

    Explanation: In 2 days they do 1/10 + 1/15 = 1/6. In 10 days they do 5/6. Remaining 1/6 is done in 2 more days with A then B pattern, so 12 days.

  7. Pipes

    7. Two pipes fill a tank in 20 and 30 minutes respectively. Together they fill it in:

    • A. 10 min
    • B. 12 min (Correct)
    • C. 15 min
    • D. 18 min

    Explanation: Combined rate = 1/20 + 1/30 = 1/12.

  8. Work Sharing

    8. A, B, and C can do a work in 12, 18, and 36 days respectively. Together they finish it in:

    • A. 4 days
    • B. 5 days
    • C. 6 days (Correct)
    • D. 7 days

    Explanation: 1/12 + 1/18 + 1/36 = 3/36 + 2/36 + 1/36 = 6/36 = 1/6, so the work finishes in 6 days.

  9. Efficiency

    9. If A is thrice as efficient as B, then A can finish the work in 12 days and B in:

    • A. 24
    • B. 30
    • C. 36 (Correct)
    • D. 40

    Explanation: If A is 3 times efficient, B takes 3 times the time = 36 days.

  10. Man-days

    10. 15 workers can finish a work in 8 days. How many workers are needed to finish it in 6 days?

    • A. 18
    • B. 20 (Correct)
    • C. 22
    • D. 24

    Explanation: Workers × days = constant, so 15 × 8 / 6 = 20.

  11. Pipes and Cisterns

    11. A pipe fills a cistern in 4 hours and another in 6 hours. A waste pipe empties it in 12 hours. All three together fill it in:

    • A. 2 hours
    • B. 2.4 hours
    • C. 3 hours (Correct)
    • D. 3.5 hours

    Explanation: Net rate = 1/4 + 1/6 - 1/12 = 5/12 - 1/12 = 4/12 = 1/3, so time is 3 hours.

  12. Work Rate

    12. If a man can do 1/20 of a work in a day, he will finish the whole work in:

    • A. 10
    • B. 15
    • C. 20 (Correct)
    • D. 25

    Explanation: Total time is reciprocal of one-day work = 20 days.

  13. Combined Efficiency

    13. A and B together do a work in 8 days. If A alone takes 24 days, B alone takes:

    • A. 10
    • B. 12 (Correct)
    • C. 16
    • D. 24

    Explanation: 1/B = 1/8 - 1/24 = 2/24 = 1/12, so B takes 12 days.

  14. Part Work

    14. A can do a work in 20 days. After working 5 days, B joins and they finish the remaining work in 5 days. B alone can do the work in:

    • A. 10 (Correct)
    • B. 15
    • C. 20
    • D. 25

    Explanation: A does 5/20 = 1/4 in 5 days, remaining = 3/4. A+B do 3/4 in 5 days, so rate = 3/20. B = 3/20 - 1/20 = 1/10, so B takes 10 days.

  15. Group Work

    15. 12 men or 18 women can complete a work in 10 days. Ratio of efficiency of a man to a woman is:

    • A. 2:3
    • B. 3:2 (Correct)
    • C. 3:5
    • D. 5:3

    Explanation: Since 12 men = 18 women, 1 man = 18/12 women = 3/2 women.