Live Practice Test

SSC CGL Time and Work Verified Practice Test 5

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Practice and revisionDetailed answer reviewMobile-friendly flow
SSC CGL Practice Session

SSC CGL Time and Work Verified Practice Test 5

15 structurally validated Time and Work questions with unique options, mapped answers and explanations.

Questions
15
Marking
+2 correct, -0.5 wrong
Format
15-question practice session
Preview all 15 questions in SSC CGL Time and Work Verified Practice Test 5 (no login required)
  1. Efficiency

    1. If A completes 1/20 of a work in one day, A alone will take:

    • A. 10 days
    • B. 15 days
    • C. 20 days (Correct)
    • D. 25 days

    Explanation: Total time is the reciprocal of one-day work.

  2. Man-days

    2. 16 workers complete a job in 15 days. 20 workers will complete it in:

    • A. 10 days
    • B. 12 days (Correct)
    • C. 14 days
    • D. 16 days

    Explanation: Workers x days remains constant, so 16 x 15 / 20 = 12.

  3. Pipes

    3. Two taps can fill a tank in 8 hours and 24 hours. Working together, they will fill it in:

    • A. 5 hours
    • B. 6 hours (Correct)
    • C. 7 hours
    • D. 8 hours

    Explanation: Combined rate = 1/8 + 1/24 = 1/6.

  4. Efficiency Ratio

    4. If A is twice as efficient as B, the efficiency ratio A:B is:

    • A. 1:2
    • B. 2:1 (Correct)
    • C. 2:3
    • D. 3:2

    Explanation: Twice as efficient means the ratio is 2:1.

  5. Alternate Days

    5. A can finish a work in 8 days and B in 12 days. Working on alternate days starting with A, how much work is completed in the first 2 days?

    • A. 1/6
    • B. 5/24 (Correct)
    • C. 1/3
    • D. 7/24

    Explanation: In one cycle, A does 1/8 and B does 1/12, so total = 5/24.

  6. Work Sharing

    6. A, B, and C can finish a work in 15, 20, and 30 days. Together they finish it in:

    • A. 5 days
    • B. 6 days (Correct)
    • C. 7 days
    • D. 8 days

    Explanation: Combined rate = 1/15 + 1/20 + 1/30 = 1/6.

  7. Pipes and Waste

    7. A pipe fills a tank in 4 hours and a waste pipe empties it in 12 hours. If both are opened, the tank fills in:

    • A. 4 hours
    • B. 5 hours
    • C. 6 hours (Correct)
    • D. 8 hours

    Explanation: Net rate = 1/4 - 1/12 = 1/6.

  8. Efficiency

    8. If B takes 30 days and A is 50% more efficient than B, A takes:

    • A. 18 days
    • B. 20 days (Correct)
    • C. 22 days
    • D. 24 days

    Explanation: A's efficiency is 3:2, so time ratio is 2:3. A takes 20 days.

  9. Part Work

    9. A can do a work in 30 days. After 10 days, B joins and they complete the rest in 10 more days. B alone can do the work in:

    • A. 15 days
    • B. 20 days
    • C. 25 days
    • D. 30 days (Correct)

    Explanation: A does 1/3 in 10 days. Remaining 2/3 is done in 10 days, so A+B = 1/15. Since A = 1/30, B = 1/30.

  10. Group Work

    10. 18 labourers finish a work in 10 days. 12 labourers will finish it in:

    • A. 12 days
    • B. 14 days
    • C. 15 days (Correct)
    • D. 18 days

    Explanation: 18 x 10 / 12 = 15.

  11. Pipes

    11. A tap fills 1/5 of a tank in one hour. It will fill the tank in:

    • A. 4 hours
    • B. 5 hours (Correct)
    • C. 6 hours
    • D. 10 hours

    Explanation: Reciprocal of one-hour work gives total time.

  12. Combined Work

    12. A and B together complete a work in 4 days. If A alone takes 12 days, B alone takes:

    • A. 4 days
    • B. 5 days
    • C. 6 days (Correct)
    • D. 7 days

    Explanation: 1/B = 1/4 - 1/12 = 1/6.

  13. Women and Men

    13. 10 men can finish a work in the same time as 15 women. Efficiency ratio of one man to one woman is:

    • A. 2:3
    • B. 3:2 (Correct)
    • C. 4:3
    • D. 5:3

    Explanation: If 10 men = 15 women, then one man = 15/10 women = 3/2 women.

  14. Efficiency

    14. If A does 20% more work than B in the same time, A:B efficiency ratio is:

    • A. 5:4
    • B. 6:5 (Correct)
    • C. 4:3
    • D. 3:2

    Explanation: 120:100 simplifies to 6:5.

  15. Basic Work

    15. A can complete a work in 12 days. What part of the work does A complete in 1 day?

    • A. 1/10
    • B. 1/12 (Correct)
    • C. 1/14
    • D. 1/15

    Explanation: One-day work is the reciprocal of total days.